Dispute Adjudication Boards in (international) construction agreements

26 Feb '19

What is a Dispute Adjudication Board?

A Dispute Adjudication Board (‘DAB’) is meant to prevent disputes from escalating and it is established to promote the resolution of disputes while construction is still underway. Because of its promptly response, it is often useful as a method to prevent a dispute to be brought to court or an arbitral tribunal. One of the reasons why the DAB is considered to be a success, is the high level of acceptance of its decisions by the parties. Both parties chose – by agreement – to use a DAB as a method of (alternative) dispute resolution and the parties appoint the members of the DAB themselves. Furthermore, the DAB will likely provide a thorough substantiation of its decision as a result of the legal and technical experience of its members and their involvement in the project, which makes the decision even more acceptable for the parties involved.

The difference between a Dispute Adjudication Board and a Dispute Review Board

The DAB must however not be confused with the Dispute Review Board (‘DRB’). The main difference between those two boards is that the DRB gives recommendations – non-binding advice – and the DAB makes (conditionally) binding decisions regarding disputes.

A DAB decision is (conditionally) binding on parties

A DAB decision is (conditionally) binding on the parties and they have to promptly give effect to it. If a party does not agree with the decision of the DAB, it may send a ‘Notice of Dissatisfaction’ within a contractually agreed term after the decision has been rendered. Nevertheless, the decision of the DAB will still be binding on both parties. This only changes if the decision has – in a later stage – been revised. If you would like to know more about Dispute Adjudication Boards in international construction agreements, our partner and Construction law specialist Jacob Henriquez has written an annotation on this matter regarding a judgement of the Court of First Instance of Curaçao (ECLI:NL:OGEAC:2018:19). This annotation was published in the Dutch Construction Law Review in February 2019 (TBR 2019/24).

Share this article

Met uw inschrijving blijft u op de hoogte van de laatste juridische ontwikkelingen op dit gebied. Vul hieronder uw gegevens in om per e-mail op te hoogte te blijven.

Personal data

 

Company details

For more information on how we use your personal information, please see our Privacy statement. You can change your preferences at any time via the 'Edit profile' link or unsubscribe via the 'Unsubscribe' link. You will find these links at the bottom of every message you receive from Ploum.

* This field is required

Interested in

Personal data

 

Company details

For more information on how we use your personal information, please see our Privacy statement. You can change your preferences at any time via the 'Edit profile' link or unsubscribe via the 'Unsubscribe' link. You will find these links at the bottom of every message you receive from Ploum.

* This field is required

Interested in

Create account

Get all your tailored information with a My Ploum account. Arranged within a minute.

I already have an account

Benefits of My Ploum

  • Follow what you find interesting
  • Get recommendations based on your interests

*This field is required

I already have an account

Benefits of My Ploum

Follow what you find interesting

Receive recommendations based on your interests

{phrase:advantage_3}

{phrase:advantage_4}


Why do we need your name?

We ask for your first name and last name so we can use this information when you register for a Ploum event or a Ploum academy.

Password

A password will automatically be created for you. As soon as your account has been created you will receive this password in a welcome e-mail. You can use it to log in immediately. If you wish, you can also change this password yourself via the password forgotten function.